CoreWeave’s Fuel Cell Strategy: Powering the 2025 AI Boom Beyond the Grid

Industry Adoption: CoreWeave’s Pivot from Strategic Bet to Commercial Necessity in Fuel Cell Power

Between 2021 and 2024, CoreWeave’s engagement with fuel cell technology was a forward-looking strategic bet. The pivotal moment came in July 2024 with the announcement of a partnership with Bloom Energy to deploy solid oxide fuel cells (SOFCs) at its upcoming Volo, Illinois data center. This move was a direct response to anticipated power-sourcing challenges, particularly the long lead times and capacity limits of traditional utility grids, which threatened to stall CoreWeave’s aggressive expansion plans to nearly double its data center footprint to 28 facilities in 2024. At this stage, the initiative was framed as an innovative solution to ensure power resilience and accelerate deployment, with the Volo project serving as the first test case.

Entering 2025, that strategic bet has transformed into a core tenet of CoreWeave’s commercial and operational strategy. The adoption of fuel cells is no longer a theoretical advantage but a demonstrated competitive weapon. The Volo, Illinois project has been quantified as a 14 MW installation, a significant commercial-scale deployment. The key driver has shifted from merely securing power to achieving unprecedented speed-to-market; CoreWeave now leverages its partnership with Bloom Energy to energize entire AI data centers in under 90 days. This capability is critical for monetizing its vast and expensive inventory of NVIDIA GPUs faster than grid-dependent competitors. This approach has been validated by other tech giants like Oracle and Equinix, who are also using Bloom’s technology to power their AI expansions. The strategy’s sophistication is evident in its flexibility; the decision to forgo on-site generation at the planned $6 billion Lancaster facility indicates a nuanced, site-specific approach, where fuel cells are deployed as a tactical tool to overcome grid constraints rather than a one-size-fits-all mandate. This signals a mature, data-driven approach to infrastructure investment, where the opportunity cost of idle hardware dictates the power strategy.

CoreWeave’s Strategic Investments in Power Infrastructure

CoreWeave’s investment strategy has become increasingly aggressive, with a clear focus on securing the power and cooling infrastructure necessary to support its large-scale AI compute services. These investments are not just in buildings but in the enabling power systems that determine how quickly revenue-generating hardware can be brought online. The data reveals a mix of direct and partner-led investments, from general infrastructure spending that highlights immense operational costs to multi-billion-dollar data center projects where power solutions like fuel cells are a critical consideration.

Table: CoreWeave’s Key Infrastructure Investments (2024-2025)

Partner / Project Time Frame Details and Strategic Purpose Source
Lancaster Data Center July 2025 A planned $6 billion AI data center in Lancaster County, PA. This facility will notably not use on-site generation like fuel cells, indicating a flexible, location-dependent power strategy where grid availability is sufficient. CoreWeave plans $6B AI data center in Lancaster
Kenilworth, NJ Data Center May 2025 A $1.2 billion investment in a 280,000-square-foot facility with Flexential. The site is designed for high-density AI, making advanced power solutions like fuel cells a viable option to meet extreme energy demands. Inside the Flexential-CoreWeave Alliance: Scaling AI …
General Infrastructure Spending Q1 2025 CoreWeave spent approximately $1.5 billion on the cost of running its infrastructure. This massive opex underscores the financial imperative behind adopting more efficient and rapidly deployable power technologies like fuel cells. CoreWeave Is A Time Bomb
Volo, IL Data Center Development 2024 CoreWeave is the anchor tenant in a new data center development, part of a potential $5 billion joint venture. This is the first site where CoreWeave is deploying Bloom Energy’s fuel cells to solve power constraints. CoreWeave Continues Growth With Major Collaborative …

CoreWeave’s Strategic Partnerships in Fuel Cell Technology

CoreWeave has rapidly built an ecosystem of partners to execute its on-site power strategy and manage the immense requirements of its AI infrastructure. The cornerstone is its alliance with Bloom Energy, which directly addresses the power bottleneck. However, collaborations with data center operators, cooling specialists, and hosting providers are equally critical, creating a network that enables the deployment and operation of fuel cell-powered, high-density compute facilities. These partnerships demonstrate a holistic approach to solving the AI infrastructure challenge.

Table: CoreWeave’s Key Power and Infrastructure Partnerships (2024-2025)

Partner / Project Time Frame Details and Strategic Purpose Source
Bloom Energy (Confirmed Partnership) August 2025 CoreWeave is confirmed as a high-profile partner of Bloom Energy, alongside Oracle and Equinix, solidifying its position among tech leaders leveraging fuel cells for AI data centers. Bloom Energy Fuel Cell Initiatives for 2025: Key Projects, …
Bloom Energy (Initial Deployment) July 2025 The partnership enables CoreWeave to energize entire data centers in under 90 days, with the initial deployment at the Volo, IL, facility to bypass grid delays for GPU-intensive workloads. What if power wasn’t the holdup? How fuel cell technology …
Chirisa Technology Parks July 2025 Chirisa owns the Volo, IL data center where CoreWeave is deploying a 14 MW fuel cell installation from Bloom Energy, demonstrating a three-way collaboration to bring an AI-ready facility online quickly. Fuel Cell Installations in Data Centers: Top 10 Projects & …
Vertiv July 2025 Collaboration to orchestrate compute, power, and cooling. Vertiv’s liquid cooling solutions are critical for managing the high-density systems powered by on-site sources like fuel cells, enabling the first cloud deployment of NVIDIA’s GB300 NVL72. How Vertiv and CoreWeave are orchestrating AI innovation
Flexential May 2025 Expanded alliance to scale AI infrastructure using high-density, liquid-cooled systems. This complements the use of on-site power generation to meet intense energy requirements at joint facilities like the one in Kenilworth, NJ. Inside the Flexential-CoreWeave Alliance: Scaling AI …
Core Scientific February 2025 Expanded hosting agreement providing CoreWeave with up to 70 MW of infrastructure at sites like Denton, TX, creating more potential locations for deploying alternative power solutions to support its GPUs. CoreWeave Is A Time Bomb
Bloom Energy (Initial Announcement) July 2024 The initial partnership was announced to provide clean, on-site power for high-performance data centers, marking CoreWeave’s strategic entry into using fuel cells to bypass grid constraints. Bloom Energy and CoreWeave Partner to Revolutionize AI …

Geographic Expansion: CoreWeave’s Site-Specific Power Strategy

In the 2021-2024 period, CoreWeave’s fuel cell strategy was geographically concentrated on a single, strategic starting point: Volo, Illinois. The announcement of the Bloom Energy partnership in July 2024 was explicitly tied to this new data center, developed as part of a major US-focused joint venture. This made the American Midwest the initial proving ground for its on-site power generation model, chosen to solve a specific regional power procurement challenge.

By 2025, CoreWeave’s geographic footprint has expanded, but its power strategy has become more regionally nuanced rather than monolithic. While the 14 MW fuel cell project moves forward in Illinois, the company’s planned $6 billion investment in Lancaster, Pennsylvania, will rely on traditional grid power. This contrast reveals a sophisticated, site-dependent decision-making process. CoreWeave is not deploying fuel cells everywhere; it is using them as a tactical scalpel in regions where the grid is a bottleneck. Its activity remains concentrated in the US, with high-density deployments also underway in New Jersey (with Flexential) and Texas (with Core Scientific), all of which represent potential future sites for on-site power. This shows that the key geographic insight is not where CoreWeave is building, but *how* it decides to power each location based on local utility timelines, costs, and capacity.

Technology Maturity: CoreWeave’s Shift to Commercial-Scale Fuel Cells

From 2021 to 2024, CoreWeave’s involvement with fuel cells was in the strategic adoption phase. The July 2024 partnership with Bloom Energy represented a commitment to deploy a specific technology—Solid Oxide Fuel Cells (SOFCs)—to solve a known business problem. The plan for the Volo, Illinois site, with a target operational date of Q3 2025, was effectively a commercial pilot at scale. The technology was chosen for its clean and reliable characteristics, but its practical application within CoreWeave’s infrastructure was still a future milestone, not a current reality.

In 2025, the technology has moved firmly into the commercial-scale deployment and validation phase. The Volo project is no longer a plan but a tangible 14 MW installation in progress. The maturity of this strategy is validated by two key factors: speed and selectivity. Bloom Energy’s ability to deliver power in under 90 days is a proven commercial capability that directly addresses CoreWeave’s need to deploy its latest NVIDIA GB300 NVL72 systems, whose immense power demands make stable on-site generation a near necessity. Furthermore, CoreWeave’s decision to opt for grid power in Lancaster demonstrates that fuel cells are now a commercially evaluated tool, deployed based on a clear ROI analysis rather than as a mandated technology for every new build. This signifies that SOFCs have graduated from a novel solution to a mature, integrated part of CoreWeave’s infrastructure toolkit.

Table: SWOT Analysis: CoreWeave’s Fuel Cell Strategy

SWOT Category 2021 – 2024 2025 – Today What Changed / Validated
Strengths Announced an innovative partnership with a fuel cell leader, Bloom Energy, to secure reliable on-site power for future AI data centers, starting with the Volo, IL site. Demonstrated ability to energize data centers in under 90 days, creating a critical time-to-market advantage. This operational agility is validated by similar moves from tech giants like Oracle and Equinix. The strength evolved from a strategic vision to a proven, quantifiable competitive advantage in deployment speed, directly enabling faster monetization of high-value NVIDIA GPUs.
Weaknesses Committed to a high-CAPEX strategy with the Bloom Energy partnership, creating financial risk before the on-site power model was proven within its operations. Reports show aggressive spending, with $1.5 billion in infrastructure costs, raising concerns about overleveraging if AI demand slows. The $6 billion Lancaster project shows fuel cells are not always the chosen solution. The financial risk is no longer theoretical but is now quantified in spending data, becoming a key point of scrutiny for investors ahead of a potential IPO. The strategy’s limitations are also clearer.
Opportunities The primary opportunity was to bypass long utility lead times to support a rapid expansion from 14 to 28 data centers in 2024. Capitalizes on the fast-growing Fuel Cell Generator Market (projected to hit $1.80 billion by 2030) and builds resilience, positioning CoreWeave as a more reliable partner for the AI industry’s power-hungry demands. The opportunity has matured from simply enabling expansion to creating a distinct competitive differentiator in reliability and speed, enhancing its value proposition in the AI cloud market.
Threats The main threat was project execution risk, including potential delays in the Volo fuel cell deployment (scheduled for Q3 2025) and reliance on a single partner. The primary threat is now market-based: a potential slowdown in AI compute demand could leave CoreWeave over-extended with expensive, specialized power assets. Competition is also emerging, with firms like FuelCell Energy targeting the AI data center market. The threat landscape has shifted from internal execution risk to external market and competitive risks, reflecting the strategy’s successful initial implementation but new long-term vulnerabilities.

2026 Outlook: What’s Next for CoreWeave’s On-Site Power Strategy?

The data from 2025 provides clear signals about what to expect from CoreWeave’s energy strategy in the year ahead. The central theme is the transition from a single-partner pilot to a mature, multi-faceted power procurement model. Market actors should first watch the completion and performance of the 14 MW Volo, Illinois project. Its operational success, cost-effectiveness, and reliability will be the ultimate proof point, directly influencing the company’s willingness to replicate this model at other grid-constrained sites.

Second, expect to see CoreWeave either deepen its partnership with Bloom Energy or diversify its fuel cell suppliers. As Bloom Energy plans to double its manufacturing capacity to 2 GW by 2026, partly to serve AI clients, CoreWeave is in a prime position to secure a larger pipeline of on-site power. The emergence of competitors like FuelCell Energy in the AI data center space may also give CoreWeave more options and better leverage.

Finally, the most telling signal will be the power strategy for future data center announcements. The decision to use grid power at the massive Lancaster facility was pivotal. Future site selections will reveal the specific economic and logistical thresholds—such as utility interconnection queues longer than 12 months or unavailable capacity—that trigger the deployment of fuel cells. This will clarify how CoreWeave balances the long-term cost of grid power against the immediate revenue enabled by on-site generation. For investors and competitors, CoreWeave’s upcoming IPO financials will be the ultimate scorecard, revealing whether this aggressive, high-CAPEX power strategy delivers the outsized returns needed to justify the risk.

Frequently Asked Questions

Why is CoreWeave using fuel cells instead of just relying on the traditional power grid?
The primary reason is speed-to-market. Traditional utility grids often have long lead times and capacity limits that can stall data center deployment. By using on-site fuel cells from Bloom Energy, CoreWeave can energize entire AI data centers in under 90 days, allowing them to monetize their expensive NVIDIA GPU inventory much faster than grid-dependent competitors.

Is CoreWeave deploying fuel cells at all of its new data centers?
No, the company employs a nuanced, site-specific strategy. While it is using a 14 MW fuel cell installation at its Volo, Illinois facility to bypass grid delays, its planned $6 billion data center in Lancaster, Pennsylvania, will use traditional grid power. This indicates that fuel cells are used as a tactical tool in regions where grid access is a bottleneck, not as a one-size-fits-all solution.

Who is CoreWeave’s main partner for this on-site power strategy?
CoreWeave’s cornerstone partner is Bloom Energy, a leader in Solid Oxide Fuel Cell (SOFC) technology. This partnership enables CoreWeave to deploy reliable, on-site power quickly. Other key partners mentioned include Vertiv for cooling solutions and data center operators like Chirisa and Flexential, who help create the high-density environments where this power is needed.

How large is CoreWeave’s first fuel cell project?
CoreWeave’s first fuel cell deployment, located at its Volo, Illinois data center, is a 14 MW installation. This is a significant commercial-scale project that moves the strategy from a conceptual plan to a tangible, operational reality designed to power an entire AI-focused facility.

What are the primary risks associated with CoreWeave’s fuel cell strategy?
The main risks are financial and market-based. The strategy involves high capital expenditure and aggressive spending on infrastructure (around $1.5 billion in Q1 2025). A potential slowdown in AI compute demand could leave CoreWeave over-extended with expensive, specialized power assets. Additionally, competition is emerging from other fuel cell companies also targeting the AI data center market.

Experience In-Depth, Real-Time Analysis

For just $200/year (not $200/hour). Stop wasting time with alternatives:

  • Consultancies take weeks and cost thousands.
  • ChatGPT and Perplexity lack depth.
  • Googling wastes hours with scattered results.

Enki delivers fresh, evidence-based insights covering your market, your customers, and your competitors.

Trusted by Fortune 500 teams. Market-specific intelligence.

Explore Your Market →

One-week free trial. Cancel anytime.


Erhan Eren

Ready to uncover market signals like these in your own clean tech niche?
Let Enki Research Assistant do the heavy lifting.
Whether you’re tracking hydrogen, fuel cells, CCUS, or next-gen batteries—Enki delivers tailored insights from global project data, fast.
Email erhan@enkiai.com for your one-week trial.

Privacy Preference Center