Offshore Wind Policy Reversal, 30.5 GW Pipeline Cut, 5 Major Projects Suspended, including Empire Wind by Equinor (2024-2025)
US Offshore Wind Projects, 30.5 GW Pipeline Reduction Following 2025 Federal Policy Shift
The U.S. offshore wind industry experienced a complete reversal of fortune, where the significant progress of 2024 was systematically dismantled by federal policy actions in 2025. This policy whiplash erased nearly 30.5 GW of planned capacity from the development pipeline, halting projects that were already under construction and freezing all new leasing activity on the Outer Continental Shelf.
Breakthrough Year of 2024
Momentum for U.S. offshore wind peaked in 2024, building on years of state-level planning and federal support. The year was marked by the successful commissioning and full operation of the nation’s first utility-scale project in federal waters. This progress solidified a development pipeline that appeared robust and poised for exponential growth, attracting billions in planned investment from major global energy firms.
- In March 2024, the 132 MW South Fork Wind project, a joint venture between Ørsted and Eversource, became fully operational, supplying power to New York.
- By the end of 2024, the total installed offshore wind capacity in the U.S. reached approximately 1 GW, with a total development pipeline of over 58 GW across 37 distinct projects.
- New state solicitations in New York and New Jersey spurred further activity, with developers like Atlantic Shores Offshore Wind and Attentive Energy submitting bids for new multi-gigawatt projects.
The 2025 Policy Reversal
The trajectory of the industry was abruptly altered in 2025 through a series of executive and administrative actions. These moves effectively froze the entire sector, targeting both future development and projects that had already secured financing and begun construction. The actions created extreme regulatory uncertainty, causing a catastrophic contraction of the project pipeline.
- On January 20, 2025, a presidential memorandum ordered the temporary withdrawal of all areas on the Outer Continental Shelf from new offshore wind leasing.
- On July 30, 2025, the Bureau of Ocean Energy Management (BOEM) rescinded all previously Designated Wind Energy Areas, formally halting the process for future site auctions.
- In December 2025, the Department of the Interior suspended the leases for five large-scale projects already under construction, including Equinor‘s prominent Empire Wind project, citing national security reviews.
- As a result of these actions, the planned U.S. offshore wind pipeline was slashed from 55.9 GW (45 projects) in Q 3 2024 to just 25.4 GW (23 projects) by late 2025.
| Data Source⇅ | Market Segment⇅ | 2024 Capacity (GW)⇅ | 2025 Forecast (GW)⇅ | Source⇅ |
|---|---|---|---|---|
| Wood Mackenzie | Onshore Wind | 5.15 * | 7 | US Expected to Install Over 7 GW of Wind Capacity in 2025 … ↗ |
| EIA | Total Wind (Utility-Scale) | 7.70 | Wind power gains ground in USA electricity mix in early 2025 ↗ | |
| Electrek | Offshore Wind | 0.10 | 0.90 | The US wind industry’s 5-year outlook is now a total roller- … ↗ |
$400 M in Impairments, US Offshore Wind Project Cancellations Following Federal Halt
The direct consequence of the 2025 federal policy shift was the suspension of active construction and the cancellation of planned projects, forcing developers to record hundreds of millions of dollars in financial impairments. The abrupt halt has led to a cascade of write-downs and has likely triggered the offshore wind crisis top 10 US projects cancelled 2025, jeopardizing billions in capital already committed to the U.S. market.
Federal Suspensions of Active Projects
The most severe impact came from the suspension of projects that were already in the construction phase. These actions by the Department of the Interior in December 2025 stopped work on some of the largest planned renewable energy projects in the country, affecting developers who had already navigated years of permitting and secured offtake agreements with states.
- Equinor’s 810 MW Empire Wind 1 project, which had reached a final investment decision and secured $3 billion in financing in early 2025, was among the five projects whose leases were suspended.
- The 704 MW Revolution Wind project, a partnership between Ørsted and Eversource, had its first turbine installed in September 2024 but faced an uncertain future following the broader federal freeze.
Developer Financial Impairments
In response to the policy instability and direct project halts, developers began to publicly account for the financial damage. Companies that had invested heavily in lease acquisitions, supply chain contracts, and development activities were forced to pause projects and re-evaluate their entire U.S. portfolio, leading to significant financial losses.
- In May 2025, National Grid announced it had taken a EUR 360 million (approximately $400 million) impairment charge after its Community Offshore Wind project, a joint venture with RWE, was paused.
- By April 2026, developer EDP had also paused three of its U.S. offshore wind projects in response to the deteriorating market conditions and regulatory uncertainty.
Table: Key U.S. Offshore Wind Project Suspensions and Pauses (2025)
| Partner / Project | Time Frame | Details and Strategic Purpose | Source |
|---|---|---|---|
| EDP Projects | Q 2 2026 | Developer paused three U.S. offshore wind projects due to market uncertainty and regulatory shifts following the 2025 federal actions. | re NEWS |
| Empire Wind (Equinor) | Q 4 2025 | Lease suspended by the Department of the Interior as part of a review of five projects under construction, halting a project that had already secured billions in financing. | Georgetown Climate Center |
| Community Offshore Wind (RWE, National Grid) | Q 2 2025 | Project was paused by its developers, leading National Grid to book a EUR 360 million impairment due to the challenging regulatory environment. | Offshore Wind.biz |
| All New Leasing | Q 1 2025 | A presidential memorandum withdrew all areas of the Outer Continental Shelf from new offshore wind leasing, freezing the primary mechanism for future project development. | The White House |
| Rank⇅ | Project Name⇅ | Market Segment⇅ | Lead Developer(s)⇅ | Capacity (MW)⇅ | Location⇅ | Status & Key Developments (2024-2025)⇅ | Source⇅ |
|---|---|---|---|---|---|---|---|
| 1 | Empire Wind 2 | Offshore Wind Generation | Equinor | 1260 | New York | In development. Part of a >2 GW project with Empire Wind 1. Received a stop-work order from the Department of the Interior in December 2025 due to a federal pause on offshore wind leases. | Empire receives stop work order from US Department of … ↗ |
| 2 | Starboard Wind | Offshore Wind Generation | Ørsted | 1184 | Connecticut | Proposed by Ørsted in March 2024 with an expected in-operation date in 2025. Status is uncertain following the December 2025 federal freeze. | Ørsted Proposes New Connecticut Offshore Wind Farm to … ↗ |
| 3 | Sunrise Wind | Offshore Wind Generation | Ørsted | 924 | New York | Under construction. Expected to be online by 2027, powering around 600,000 homes. It was one of the five projects affected by the December 2025 federal freeze. | Sunrise Wind: New York’s Largest Offshore Wind Project ↗ |
| 4 | Empire Wind 1 | Offshore Wind Generation | Equinor | 810 | New York | Secured a $3 billion financing deal in January 2025. Received a stop-work order in December 2025, halting construction activities. | US freezes five big offshore wind projects, shares dive ↗ |
| 5 | Revolution Wind | Offshore Wind Generation | Ørsted, Eversource | 704 | Rhode Island | Under construction, expected online in fall 2025. First Siemens Gamesa turbine installed in September 2024. A stop-work order was issued in August 2025 but overturned by a judge in September 2025, allowing work to resume. | Trump’s order to halt offshore wind project overturned … ↗ |
| 6 | South Fork Wind | Offshore Wind Generation | Ørsted, Eversource | 132 | New York | Operational. A September 2025 report on its first full year of operation noted a 46.4% net capacity factor. | One year of South Fork Wind ↗ |
| 7 | US Wind Project (MarWin) | Offshore Wind Generation | US Wind | Maryland/Delaware | In development. US Wind signed a deal with Delaware worth approximately $128 million in January 2025, covering lease payments, grid upgrades, and community benefits for its project comprised of up to 121 turbines. | Delaware inks deal with US Wind worth $128 million ↗ |
East Coast Focus, US Offshore Wind Stalls in New York and New Jersey
The U.S. offshore wind market is almost exclusively concentrated along the Atlantic coast, where strong state-level policies and favorable wind resources created hubs of activity. The 2025 federal actions directly targeted these leading regions, undermining years of planning and investment by states like New York, New Jersey, and Massachusetts, which had been the primary drivers of demand.
State-Led Momentum Pre-2025
Before the federal reversal, East Coast states were in a race to procure offshore wind energy to meet ambitious clean energy targets. States ran competitive solicitations for long-term power purchase agreements, creating a clear demand signal that attracted global developers and was set to anchor a domestic supply chain. This momentum established the foundation for the offshore wind top 10 projects in USA in 2025.
- In January 2024, New Jersey’s Board of Public Utilities approved two large-scale projects: the 1, 342 MW Attentive Energy Two and the 2, 400 MW Leading Light Wind.
- New York was also advancing its procurement efforts, making awards under its fourth offshore wind solicitation (NY 4) in early 2024 to projects like Sunrise Wind and Empire Wind 1.
Federal Actions Undermine Regional Hubs
The federal freeze on new leasing and suspension of active projects created a direct conflict with state-level energy policies. Projects that states were counting on to meet their climate and energy goals were abruptly stopped, leaving significant gaps in their long-term plans and stranding related investments in port infrastructure and manufacturing.
- The suspension of Equinor‘s Empire Wind project was a direct blow to New York’s renewable energy goals, as the project was central to the state’s strategy.
- The uncertainty cast over projects in the New York Bight and off the coast of New Jersey effectively nullified the progress made in recent state solicitations.
- In response to the federal actions, a coalition of seven states filed a lawsuit in mid-2026 to challenge the administration’s policies, highlighting the deep rift between federal and state governments on offshore wind development.
| Forecast Provider⇅ | Market Segment⇅ | 2024 Market Size ($B)⇅ | 2026 Forecast ($B)⇅ | 2030 Forecast ($B)⇅ | CAGR (%)⇅ | Source⇅ |
|---|---|---|---|---|---|---|
| Grand View Research | Offshore Wind Turbine | 19.90 | 24.70 | 38.10 | 11.50 | Offshore Wind Turbine Market Size, Share Report 2025-2030 ↗ |
| GM Insights | Overall Wind Energy | 174.50 | 215.39 * | 328.16 * | 11.10 | Wind Energy Market Size, Growth Outlook 2025-2034 ↗ |
US Offshore Wind, 1 GW Operational Capacity Faces Stalled Commercial Scale-Up (2024-2025)
While offshore wind turbine and foundation technology is mature on a global scale, the U.S. market’s path from initial deployments to widespread commercialization was effectively blocked by the 2025 policy shift. The successful operation of the first utility-scale projects in 2024 validated the technology’s viability in U.S. waters, but non-technical, political barriers now stand as the primary constraint to further deployment.
Validation at Utility-Scale
The period leading up to 2025 demonstrated that the U.S. was capable of executing complex offshore wind projects. Major global OEMs and developers brought proven technology to the market, successfully adapting it to U.S. regulations and conditions. The commissioning of South Fork Wind and construction start on Revolution Wind were key proof points.
- The deployment of turbines from established manufacturers like Siemens Gamesa, which dominated global installations in 2024, proved the technology was ready for the U.S. market.
- The 132 MW South Fork Wind and 704 MW Revolution Wind projects confirmed that multi-hundred-megawatt farms could be permitted and built in federal waters off the East Coast.
Policy as the Primary Constraint to Deployment
The dramatic pipeline reduction in 2025 was not driven by technological failures, cost overruns, or supply chain issues, but almost exclusively by the change in federal policy. Viable, permitted, and financed projects were stopped by administrative action, demonstrating that political risk has eclipsed commercial or technical risk as the main barrier to growth.
- The halt of projects like Empire Wind occurred despite the developer having secured all necessary permits and offtake agreements, indicating the issue was political, not technical or commercial.
- The reduction of the U.S. offshore wind pipeline by nearly 55% represents a stalled commercialization path that is entirely disconnected from the underlying maturity or readiness of the technology. The industry is now defined by its exposure to regulatory and political volatility.
| Metric⇅ | Market Segment⇅ | Q3 2024⇅ | Q4 2025⇅ | Change (GW)⇅ | Change (%)⇅ | Source⇅ |
|---|---|---|---|---|---|---|
| Planned Capacity (GW) | Offshore Wind | 55.90 | 25.40 | -30.50 * | -54.60 * | Storm Clouds Gather Over U.S. Offshore Wind as Policy Shifts Cut … ↗ |
| Number of Projects | Offshore Wind | 45 | 23 | -22 * | -48.90 * | Storm Clouds Gather Over U.S. Offshore Wind as Policy Shifts Cut … ↗ |
SWOT Analysis, US Offshore Wind Strengths and Execution Risks
The U.S. offshore wind sector’s core strengths, including robust state-level demand and a vast geographic resource, were fundamentally challenged by the emergence of extreme federal political risk in 2025. This shift transformed the industry’s risk profile, turning opportunities for economic growth into weaknesses tied to regulatory instability and investor uncertainty.
- Strengths: The industry’s foundation remains the strong, legally mandated clean energy goals of key East Coast states, which continue to create demand for offshore wind power.
- Weaknesses: The nascent domestic supply chain and lack of specialized installation vessels were known weaknesses, but these are now overshadowed by the critical weakness of extreme sensitivity to federal political cycles.
- Opportunities: The primary opportunity has shifted from development to litigation, with states suing the federal government to reverse the 2025 actions and restore a path for project execution.
- Threats: The overriding threat is the federal government’s demonstrated willingness to halt permitted projects and freeze all new leasing, creating a level of political risk that may be untenable for capital-intensive, long-duration infrastructure projects.
Table: SWOT Analysis for U.S. Offshore Wind (2024–2025)
| SWOT Category | 2021 – 2024 | 2025 – Today | What Changed / Validated |
|---|---|---|---|
| Strengths | Strong state-level demand (NY, NJ, MA); developer interest from global leaders like Ørsted and Equinor; large, high-quality wind resource on the Outer Continental Shelf. | State-level demand remains, but its ability to drive projects is nullified; legal challenges from states (e.g., 7-state lawsuit) become a new form of strength. | State commitment was validated as resilient, but its power to compel federal action was proven to be limited. The primary strength shifted from market-based to legal-based. |
| Weaknesses | Nascent domestic supply chain; high LCOE compared to onshore renewables; lengthy and complex federal permitting process under BOEM. | Extreme regulatory and political uncertainty; investor confidence destroyed; project pipeline slashed by over half (30.5 GW); financial impairments for developers. | The key weakness shifted from being executional (permitting, supply chain) to existential (political risk). The federal government itself became the primary source of project failure. |
| Opportunities | Federal goal of 30 GW by 2030; creation of thousands of manufacturing and port jobs; energy security and independence. | Legal challenges to overturn federal actions; potential for developers to declare force majeure and exit PPAs; capital reallocation to more stable markets like Europe. | Opportunities for growth evaporated and were replaced by opportunities for litigation and capital flight. The focus shifted from building projects to mitigating losses. |
| Threats | Supply chain inflation; rising interest rates; stakeholder opposition (e.g., fishing industry, coastal communities). | Federal government actions: lease suspensions, leasing moratorium, rescinding of Wind Energy Areas; potential for complete developer exit from the U.S. market. | The primary threat was validated to be political risk. Economic headwinds like inflation were superseded by a direct, government-led halt to the entire industry. |
| Project Name⇅ | Capacity (MW)⇅ | Developer(s)⇅ | Location⇅ | Status & Key 2024-2025 Developments⇅ | Source⇅ |
|---|---|---|---|---|---|
| Coastal Virginia Offshore Wind (CVOW) | 2640 | Dominion Energy (NextEra Energy to acquire) | Virginia | Under Construction. Construction began in 2024 with an expected completion by 2026. It is the largest project currently under construction. | BUILDING OFFSHORE WIND – Virginia Conservation Network ↗ |
| SouthCoast Wind | 2400 | Ocean Winds (EDP & ENGIE JV) | Massachusetts / Rhode Island | Paused. BOEM approved the project in 2024. However, developer EDP paused the project in April 2026 due to policy uncertainty. | EDP pauses three US offshore wind projects – reNEWS ↗ |
| Attentive Energy Two | 1342 | Attentive Energy (TotalEnergies & Corio Generation) | New Jersey | Stalled. Awarded contract in NJ's 3rd solicitation in Jan 2024. The plan never received federal approval before the leasing freeze. | 7 States Sue Trump Administration over OSW Buyout – RTO Insider ↗ |
| Community Offshore Wind | 1314 | RWE & National Grid | New York Bight | Paused. In May 2025, National Grid booked a £303 million ($402 million) impairment charge after the project was shelved. | National Grid takes $400m hit on shelved US offshore wind … ↗ |
| Ocean Wind 1 | 1100 | Ørsted | New Jersey | Cancelled. Ørsted officially announced the project's cancellation, citing rising costs and supply chain issues. | Ocean Wind 1 ↗ |
| Vineyard Wind 1 | Avangrid & Copenhagen Infrastructure Partners | Massachusetts | Partially Operational. Was shut down for part of 2024. A turbine blade failure in July 2024 delayed full commercial operation to late 2025. | [PDF] Status of US Offshore Wind Projects: – Whitestrand Consulting ↗ | |
| Empire Wind 1 | 810 | Equinor | New York | Suspended. Secured $3B financing in late 2024. Construction was halted, resumed, and then officially suspended by federal order on Dec 22, 2025. | Empire Wind ↗ |
| Revolution Wind | 704 | Ørsted & Eversource | Rhode Island / Connecticut | Under Construction. It is the first multi-state offshore wind farm in the U.S. | Revolution Wind ↗ |
| Leading Light Wind | Invenergy & energyRe | New Jersey | Stalled. Awarded contract in NJ's 3rd solicitation in Jan 2024, part of a 3,742 MW joint award. Stalled by federal policy changes. | NJDEP| Offshore Wind | Project Areas – NJ.gov ↗ | |
| South Fork Wind | 132 | Ørsted & Eversource | New York | Operational. Achieved full commissioning on March 14, 2024, becoming the first utility-scale project in federal waters. | Offshore wind power in the United States – Wikipedia ↗ |
US Market Volatility Signals Underlying Project Realization Challenges
This volatility in FID capacity between 2024 and 2025 highlights the nascent and potentially unpredictable nature of the US offshore wind market. Unlike the more consistent European market, the US pipeline may be susceptible to permitting delays, supply chain constraints, or policy shifts, impacting project realization and long-term growth.
(Source: Rystad Energy — via Trump's offshore wind energy freeze: What states lose if the executive order remains in place | The Invading Sea)
3 Scenarios, US Offshore Wind Navigates Legal and Political Hurdles
The future of the U.S. offshore wind industry is no longer dependent on technology or market economics but on the outcomes of legal and political confrontations. The sector’s ability to recover from the 2025 policy shock hinges almost entirely on whether a stable and predictable federal regulatory framework can be restored.
- If states achieve a legal victory against the federal government’s 2025 actions, watch for the potential reinstatement of suspended project leases like Empire Wind. However, even with a legal win, investor confidence will be severely damaged, and developers will likely demand new risk premiums and higher offtake prices to restart projects.
- If the federal leasing moratorium and project suspensions are upheld by the courts, watch for a mass exodus of capital and expertise from the U.S. market. Developers like Equinor, Ørsted, and RWE will likely accelerate the redeployment of investment toward more predictable markets, and the U.S. will cede its potential leadership in the sector.
- If a future administration reverses the 2025 policies, watch for a slow and cautious re-engagement from investors. The industry will not simply resume where it left off; project timelines will be delayed by years, supply chain commitments will have expired, and all power purchase agreements will require complete renegotiation to reflect the heightened political risk.
| Company⇅ | Company Type⇅ | Key U.S. Projects⇅ | Significant 2024-2025 Actions & Impacts⇅ | Source⇅ |
|---|---|---|---|---|
| Equinor | Developer | Empire Wind 1 & 2 | Took 100% ownership of Empire Wind in early 2024. Secured over $3B in project financing but was forced to suspend construction in late 2025 due to a federal order, calling the action 'unlawful' and 'unprecedented'. | How Trump pushed Empire Wind to the brink of collapse ↗ |
| Ørsted | Developer | South Fork Wind, Revolution Wind, Ocean Wind 1 | Brought South Fork Wind online in March 2024 and advanced construction on Revolution Wind. However, the company cancelled the 1,100 MW Ocean Wind 1 project. | Ocean Wind 1 ↗ |
| Ocean Winds | Developer (EDP & ENGIE JV) | SouthCoast Wind | Gained BOEM approval for the 2.4 GW SouthCoast Wind project in 2024. Parent company EDP paused the project in April 2026, citing limited policy visibility. | EDP pauses three US offshore wind projects – reNEWS ↗ |
| GE Vernova | Turbine Manufacturer (OEM) | Vineyard Wind 1 | Was the dominant U.S. onshore wind turbine supplier in 2024 with 56% market share. Its offshore division had a 'tough year' in 2024 and became embroiled in a legal dispute with Vineyard Wind in 2026 over project issues. | GE Vernova Challenges Vineyard Wind’s Claims of Harm ↗ |
| Siemens Gamesa | Turbine Manufacturer (OEM) | Coastal Virginia Offshore Wind, Revolution Wind | Reclaimed its position as the top global offshore turbine supplier in 2024, installing 294 turbines worldwide. It is a key supplier for major U.S. projects still under construction. | Siemens Gamesa Dominate 2024 WTG Installation ↗ |
| National Grid | Developer / Utility | Community Offshore Wind | Took a £303 million ($402 million) impairment charge in May 2025 after its 1.3 GW Community Offshore Wind project with RWE was shelved due to the changing policy landscape. | National Grid takes $400m hit on shelved US offshore wind … ↗ |
| NextEra Energy | Developer / Utility | Coastal Virginia Offshore Wind (pending) | Positioned to become a major player in U.S. offshore wind through the acquisition of the 2,640 MW Coastal Virginia Offshore Wind project, the largest under construction. | NextEra Energy to Join the Offshore Wind Club, But Does It Matter? ↗ |
The questions your competitors are already asking
This report covers one angle of the impact of political risk on US offshore wind. The questions that matter most depend on your work.
- status of state lawsuits against federal wind policy
- offshore wind developers moving investment from US to Europe
- which US offshore wind projects are still being built
- impact of wind policy on US port and factory investments
This report does not answer these. Enki Brief Pro does.
Your question, your angle, your framework. SWOT, PESTL, scenario modelling. The same niche depth, built around the decision your work actually depends on.
Run your first brief in Enki Brief Pro
Related Articles
If you found this article helpful, you might also enjoy these related articles that dive deeper into similar topics and provide further insights.
- E-Methanol Market Analysis: Growth, Confidence, and Market Reality(2023-2025)
- Battery Storage Market Analysis: Growth, Confidence, and Market Reality(2023-2025)
- Carbon Engineering & DAC Market Trends 2025: Analysis
- Climeworks 2025: DAC Market Analysis & Future Outlook
- Climeworks- From Breakout Growth to Operational Crossroads
Erhan Eren
Erhan Eren is the CEO and Co-Founder of Enki, a commercial intelligence platform for emerging technologies and infrastructure projects, backed by Equinor, Techstars, and NVIDIA. He spent almost a decade in oil and gas, first at Baker Hughes leading market intelligence, strategy, and engineering teams, then at AI startup Maana, where he spearheaded commercial strategy to acquire net new accounts including Shell, SLB, and Saudi Aramco. It was across these roles, watching teams stitch together executive briefings from scattered PDFs and Google searches, that the idea for Enki was born. Erhan holds a BS in Aeronautical Engineering from Istanbul Technical University and an MS in Mechanical and Aerospace Engineering from Illinois Institute of Technology. He has spent over 20 years at the intersection of energy, strategy, and technology, and built Enki to give professionals the clarity they need without the analyst-grade budget or timeline.

